Financial Transparency

Budget & Financial Transparency

Tracking municipal finances and projects for accountability

Financial Report

Statement of Receipts & Expenditures

FY 2025 actual annual financial performance

₱1,837.57 M Total Receipts
₱1,807.22 M Total Expenditures
₱30.35 M Receipts Less Expenditures
₱573.72 M Ending Cash Balance

Receipt Sources

Local Sources Tax & Non-Tax Revenue
₱633.56 M 34.5%
External Sources NTA & Other National Shares
₱1,198.22 M 65.2%
Non-Income Receipts Loan Proceeds
₱5.79 M 0.3%

Expenditure Allocation

General Public Services Administration & Operations
₱1,036.29 M 57.3%
Social Services Health, Education, Welfare
₱343.77 M 19.0%
Economic Services Infrastructure & Development
₱149.77 M 8.3%
Debt & Non-Operating Operating Debt, Capital & Principal Costs
₱277.39 M 15.3%

Source: DBM/BLGF Table F.14 - Statement of Receipts and Expenditures, by Cities, 2025 . Figures are in million pesos and are based on actual data submitted by local treasurers through the LGU Integrated Financial Tools system.

National Government Allocation

Bulacan First District GAA Allocation

Capital outlays under the Bulacan 1st District Engineering Office

General Appropriations Act allocations for Bulacan First District, FY 2023 to FY 2025
Fiscal Year GAA Amount
FY 2023 ₱8.389 B
FY 2024 ₱9.652 B
FY 2025 ₱8.191 B

These are DPWH national-government capital-outlay allocations for the legislative district, not City Government of Malolos receipts, expenditures, or awarded contract values. Amounts are shown in billions of Philippine pesos, rounded to three decimal places.

Source: Philippine Center for Investigative Journalism (PCIJ), “DOCUMENTS: DPWH budget data from 2023 to 2026” (August 26, 2026) . Figures shown are from the Bulacan First District row of the FY 2023–2025 GAA budget-distribution table for Capital Outlays (Operations excluding FAPs).

Malolos budget data

Malolos budget data

BetterGov budget records returned for Malolos, shown separately from City Government revenues, expenditures, and appropriations. Partner records are displayed only after their geographic scope and source have been reviewed.

Agency-level context

Bulacan State University FY 2026 total

This comparison is separate from the Malolos search-result table below. DBM reports the university-wide total, while BetterGov's report displays its rounded agency total.

DBM F.4 exact total ₱2,036,641,000 Regular programs ₱1,676,641,000 + projects ₱360,000,000
BetterGov agency report ₱2.11B 2026 amount as displayed; rounded by BetterGov
Displayed difference ≈₱73.36M BetterGov appears higher, using its rounded ₱2.11B figure

The table combines positive FY 2026 BetterGov search records with the three DBM F.4 top-level regular-program totals. When filtered to State Universities and Colleges (SUCs), its seven rows reconcile to DBM's exact ₱2,036,641,000 total. It is not a raw BetterGov agency-total export; the DBM document remains the authority for this exact total.

Loading Malolos budget data. Checking the last approved snapshot…
Connecting to the approved snapshot…
Public Works

Infrastructure Investments

Largest awarded FY 2025 DPWH contracts located in the City of Malolos

2025 Flood Control

Flood Mitigation Structure at Barangay Canalate

Barangay Canalate, City of Malolos, Bulacan

Type of Work Construction of Flood Mitigation Structure
Contractor 11-16 Construction / KBP Builders and Trading
Contract Cost ₱92,823,238.32
2025 Flood Control

Pumping Station and Flood Gate (Phase II) at Barangay Atlag

Barangay Atlag, City of Malolos, Bulacan

Type of Work Construction of Pumping Station and Flood Gate
Contractor C.T. Leoncio Construction & Trading
Contract Cost ₱92,748,245.71
2025 Flood Control

Pumping Station and Flood Gate at Mambog Creek (Phase II)

Mambog Creek, City of Malolos, Bulacan

Type of Work Construction of Pumping Station and Flood Gate
Contractor Ferdstar Builders Inc.
Contract Cost ₱92,712,522.71
National Government Projects

Major FY 2025 DPWH Contracts in Malolos

Implementing Agency: Bulacan 1st District Engineering Office

Source: DPWH Transparency Portal . Shows the 12 highest-cost awarded FY 2025 contracts located in Malolos, verified August 19, 2026. Values are awarded contract amounts, not the City Government's full infrastructure budget.

National Government Projects

FY 2026 DPWH Infrastructure Program in Malolos

Programmed under GAA 2026 · Primarily implemented by Bulacan 1st District Engineering Office

Source: DPWH Infrastructure Program. Extracted from “FY 2026 DPWH Infrastructure Program - Region III,” pages 16-20, based on GAA, R.A. 12314; reviewed August 26, 2026. Amounts are programmed appropriations, not awarded contract values. The list includes line items explicitly located in Malolos and one multi-city road corridor that includes Malolos. Project implementation and completion status have not yet been independently verified.